In an effort to keep water users apprised of upcoming planned maintenance, the District will publish a monthly listing of the upcoming schedule for the next 45 to 60 days. The information in the June 27, 2019 monthly notice is revised according to this table.
Lateral(s) Impacted | Dates | Scheduled Work | Notes |
---|---|---|---|
Entire Coalinga Canal | 7-23 to 7-24 | Aquatic Growth Treatment | Canal Capacity Limited (100 CFS) |
Entire Coalinga Canal | 8-21 to 8-22 | Aquatic Growth Treatment | Canal Capacity Limited (100 CFS) |
1R-4.0 “C” and “D” Reaches | 7-2 to 7-3 | Aquatic Growth Treatment | 1R-4.0D Reservoir Treatment 24hr Shutdown |
1R-4.0 “C” and “D” Reaches | 7-31 to 8-1 | Aquatic Growth Treatment | 1R-4.0D Reservoir Treatment 24hr Shutdown |
1R-4.0 “C” and “D” Reaches | 8-20 to 8-21 | Aquatic Growth Treatment | 1R-4.0D Reservoir Treatment 24hr Shutdown |
2R System | 7-9 to 7-10 | Aquatic Growth Treatment | 2R-A and 2R-B Reservoir Treatment 24hr Shutdown |
2R System | 8-6 to 8-7 | Aquatic Growth Treatment | 2R-A and 2R-B Reservoir Treatment 24hr Shutdown |
17R System | 7-16 to 7-17 | Aquatic Growth Treatment | 17R-B and 17R-C Reservoir Treatment 24hr Shutdown |
17R System | 8-13 to 8-14 | Aquatic Growth Treatment | 17R-B and 17R-C Reservoir Treatment 24hr Shutdown |